Sr.no | Questions |
---|---|
1 | Q1: Static analysis is best described as: A The analysis of batch programs. B The reviewing of test plans. C The analysis of program code. D The use of black box testing. Click here for answer Correct Answer : c |
2 | Q2: Which of the following statements about reviews is true? A Reviews cannot be performed on user requirements specifications. B Reviews are the least effective way of testing code. C Reviews are unlikely to find faults in test plans. D Reviews should be performed on specifications, code, and test plans. Click here for answer Correct Answer : d |
3 | Q3: Why are static testing and dynamic testing described as complementary? A Because they share the aim of identifying defects and find the same types of defect. B Because they have different aims and differ in the types of defect they find. C Because they have different aims but find the same types of defect. D Because they share the aim of identifying defects but differ in the types of defect they find. Click here for answer Correct Answer : d |
4 | Q4: ‘Entry criteria’ should address questions such as I. Are the necessary documentation, design and requirements information available that will allow testers to operate the system and judge correct behaviour. II. Is the test environment-lab, hardware, software and system administration support ready? III. Those conditions and situations that must prevail in the testing process to allow testing to continue effectively and efficiently. IV. Are the supporting utilities, accessories and prerequisites available in forms that testers can use A I, II and IV B I, II and III C I, II, III and IV D II, III and IV. Click here for answer Correct Answer : a |
5 | Q5: Static Analysis A Same as static testing B Done by the developers C Both A. and B D None of the above Click here for answer Correct Answer : c |
6 | Q6: In formal review, Rework: fixing defects found typically done by _________ A Moderator B Author C Reviewer D Recorder Click here for answer Correct Answer : b |
7 | Q7: Which expression best matches the following characteristics or review processes: 1. Led by author 2. Undocumented 3. No management participation 4. Led by a trained moderator or leader 5. Uses entry exit criteria s) Inspection t) Peer review u) Informal review v) Walkthrough A s = 4, t = 3, u = 2 and 5, v = 1 B s = 4 and 5, t = 3, u = 2, v = 1 C s = 1 and 5, t = 3, u = 2, v = 4 D s = 5, t = 4, u = 3, v = 1 and 2 E s = 4 and 5, t = 1, u = 2, v = 3 Click here for answer Correct Answer : b |
8 | Q8: Which of the following statements is NOT true: A Inspection is the most formal review process B Inspections should be led by a trained leader C Managers can perform inspections on management documents D Inspection is appropriate even when there are no written documents E Inspection compares documents with predecessor (source) documents Click here for answer Correct Answer : d |
9 | Q9: What can static analysis NOT find? A The use of a variable before it has been defined B Unreachable ("dead") code C Whether the value stored in a variable is correct D The re-definition of a variable before it has been used E Array bound violations Click here for answer Correct Answer : c |
10 | Q10: Which rule should not be followed for reviews A Defects and issues are identified and corrected B The product is reviewed not the producer C All members of the reviewing team are responsible for the result of the review D Each review has a clear predefined objective Click here for answer Correct Answer : c |
11 | Q11: Which of the following are good candidates for manual static testing? A Requirement specifications, test plan, code, memory leaks. B Requirement specifications, test cases, user guides. C Requirement specifications, user guides, performance. D Requirement specifications, website, code, use cases. Click here for answer Correct Answer : b |
12 | Q12: Static analysis tools are typically used by A Testers B Developers C Testers & Developers D None Click here for answer Correct Answer : b |
13 | Q13: Which of the following statements are TRUE for informal reviews? I. Easy to get started and have some benefit II. Have no or minimal formal process III. The process must be documented IV. May include "paired programming" A I, II and IV B I and III C III and IV D I, III and IV Click here for answer Correct Answer : a |
14 | Q14: Who is responsible for documenting all the issues, problems and open point that were identified during the review meeting A Moderator B Scribe C Reviewers D Author Click here for answer Correct Answer : b |
15 | Q15: Which of the following is a purpose of the review planning phase? A Log defects. B Explain the documents to the participants. C Gather metrics. D Allocate the individual roles. Click here for answer Correct Answer : d |
16 | Q16: Which test requires the execution of the software component? A Formal inspection B Dynamic testing C Code walkthrough D Execution testing Click here for answer Correct Answer : b |
17 | Q17: Who typically use static analysis tools? A Customers and users B Developers and designers C Business and systems analysts D System and acceptance testers Click here for answer Correct Answer : b |
18 | Q18: For which of the following would a static analysis tool be MOST useful? A Supporting reviews. B Validating models of the software. C Testing code executed in a special test harness. D Enforcement of coding standards. Click here for answer Correct Answer : d |
19 | Q19: Typical defects that are easier to find in reviews than in dynamic testing are: A Deviations from standards, B Requirement defects, C Design defects, D All of the above. Click here for answer Correct Answer : d |
20 | Q20: Reviews, static analysis and dynamic testing have the same objective A Identifying defects. B Fixing defects. C A. and B D None of the above Click here for answer Correct Answer : a |
21 | Q21: Find the correct flow of the phases of a formal review A Planning, Review meeting, Rework, Kickoff B Planning, Individual preparation, Kickoff, Rework C Planning, Review meeting, Rework, Follow up D Planning, Individual preparation, Follow up, Kick off Click here for answer Correct Answer : c |
22 | Q22: One person has been dominating the current software process improvement meeting. Which of the following techniques should the facilitator use to bring other team members into the discussion? A Confront the person and ask that other team members be allowed to express their opinions. B Wait for the person to pause, acknowledge the person’ s opinion, and ask for someone else’ s opinion. C Switch the topic to an issue about which the person does not have a strong opinion. D Express an opinion that differs from the person’ s opinion in order to encourage others to express their ideas. Click here for answer Correct Answer : b |
23 | Q23: What is the main purpose of Informal review A Inexpensive way to get some benefit B Find defects C Learning, gaining understanding, effect finding D Discuss, make decisions, solve technical problems Click here for answer Correct Answer : a |
24 | Q24: The principle of Cyclomatic complexity, considering L as edges or links, N as nodes, P as independent paths A L- N + 2P B N - L + 2P C N - L + P D N - L + P Click here for answer Correct Answer : a |
25 | Q25: What can static analysis NOT find? A The use of a variable before it has been defined B Unreachable ("dead") code C Memory leaks D Array bound violations Click here for answer Correct Answer : c |
26 | Q26: Which of the following is true about Formal Review or Inspection:- i. Led by Trained Moderator (not the author). ii. No Pre Meeting Preparations iii. Formal Follow up process. iv. Main Objective is to find defects A ii is true and i,iii,iv are false B i,iii,iv are true and ii is false C i,iii,iv are false and ii is true D iii is true and I,ii,iv are false Click here for answer Correct Answer : b |
27 | Q27: The Phases of formal review process is mentioned below arrange them in the correct order. i. Planning ii. Review Meeting iii. Rework iv. Individual Preparations v. Kick Off vi. Follow Up A i,ii,iii,iv,v,vi B vi,i,ii,iii,iv,v C i,v,iv,ii,iii,vi D . i,ii,iii,v,iv,vi Click here for answer Correct Answer : c |
28 | Q28: Who are the persons involved in a Formal Review :- i. Manager ii. Moderator iii. Scribe / Recorder iv. Assistant Manager A i,ii,iii,iv are true B i,ii,iii are true and iv is false C ii,iii,iv are true and i is false. D i,iv are true and ii, iii are false. Click here for answer Correct Answer : b |
29 | Q29: Which of the following statements regarding static testing is false: A Static testing requires the running of tests through the code B Static testing includes desk checking C Static testing includes techniques such as reviews and inspections D Static testing can give measurements such as cyclomatic complexity Click here for answer Correct Answer : a |
30 | Q30: A Person who documents all the issues, problems and open points that were identified during a formal review. A Moderator. B Scribe C Author D Manager Click here for answer Correct Answer : b |
31 | Q31: Which statements correctly describe certain phases of a formal review? A Looking for defects occurs during kick-off phase Fixing defects found happens during rework phase B Personnel selection occurs during planning phase Gathering metrics happens during the review meeting phase C Distributing documents occurs during the planning phase Personal review happens during individual preparation phase D Personnel selection occurs during planning phase Fixing defects found happens during rework phase Click here for answer Correct Answer : d |
32 | Q32: Which of the following is a Key Characteristics of Walk Through A Scenario, Dry Run, Peer Group B Pre-Meeting Preparations C Formal Follow Up Process D Includes Metrics Click here for answer Correct Answer : a |
33 | Q33: The Planning phase of a formal review includes the following :- A Explaining the objectives B Selecting the personnel, allocating roles. C Follow up D Individual Meeting preparations Click here for answer Correct Answer : b |
34 | Q34: In which phase static tests are used A Requirements B Design C Coding D All of the above Click here for answer Correct Answer : d |
35 | Q35: Which of the following are success factors for reviews? I. Clear objectives for each review. II. Checklists and/or roles are used to increase effectiveness of defect identification. III. There is an emphasis on process improvement. IV. People issues and psychological aspects are not reviewed. A I and III B II, III and IV C I, II and III D IV Click here for answer Correct Answer : c |
36 | Q36: The person who leads the review of the document(s), planning the review, running the meeting and follow-up after the meeting A Reviewer B Author C Moderator D Auditor Click here for answer Correct Answer : c |
37 | Q37: A formal assessment of a work product conducted by one or more qualified independent reviewer to detect defects. A Inspection. B Walkthrough. C Review D Non Conformance Click here for answer Correct Answer : a |
38 | Q38: A series of probing questions about the completeness and attributes of an application system is called A Checklist B Checkpoint review C Decision table D Decision tree Click here for answer Correct Answer : a |
39 | Q39: Typical defects discovered by static analysis includes A Programming standard violations B Referring a variable with an undefined value C Security vulnerabilities D All Above Click here for answer Correct Answer : d |
40 | Q40: Which of the following are the main stages of a formal review? A Initiation, Preparation, Informal Review Meeting, Status, Rework, and Follow up. B Planning, Preparation, Technical Review, Rework, and Closure. C Preparation, Inspection, Rework, Closure, and Follow up. D Planning, Kick off, Individual Preparation, Review Meeting, Rework, and Follow up Click here for answer Correct Answer : d |
41 | Q41: Given the Following program IF X <>= Z THEN Statement 2; END McCabe’s Cyclomatic Complexity is : A 2 B 3 C 4 D 5 Click here for answer Correct Answer : a |
42 | Q42: In a review meeting a moderator is a person who A Takes minutes of the meeting B Mediates between people C Takes telephone calls D Writes the documents to be reviewed Click here for answer Correct Answer : b |
43 | Q43: Static code analysis typically identifies all but one of the following problems. Which is it? A Unreachable code B Undeclared variable C Faults in the requirements D Too few comments Click here for answer Correct Answer : c |
44 | Q44: What statement about static analysis is true? A With static analysis, defects can be found that are difficult to find with dynamic testing. B Compiling is not form of static analysis C When properly performed, static analysis makes functional testing redundant. D Static analysis finds all faults. Click here for answer Correct Answer : a |
45 | Q45: Which statement about the function of static analysis tool is true? A Gives quality information about the code without executing it. B Checks expected results against actual results. C Can detect memory leaks. D Gives information about what code has and has not been exercised. Click here for answer Correct Answer : a |
46 | Q46: Which of the following are the typical defects found by static analysis tools? (a) Variables that are never used. (b) Security vulnerabilities. (c) Poor performance. (d) Unreachable code. (e) Business processes not followed. A b, c and d are true; a and e are false B a is true; b, c, d and e are false C c, d and e are true; a and b are false D a, b and d are true; c and e are false Click here for answer Correct Answer : d |
47 | Q47: Which of the following, if observed in reviews and tests, would lead to problems (or conflict) within teams? A Testers and reviewers are not curious enough to find defects. B Testers and reviewers are not qualified enough to find failures and faults. C Testers and reviewers communicate defects as criticism against persons and not against the software product. D Testers and reviewers expect that defects in the software product have already been found and fixed by the developers Click here for answer Correct Answer : c |
48 | Q48: Which of the following are the main phases of a formal review? A Initiation, status, preparation, review meeting, rework, follow up. B Planning, preparation, review meeting, rework, closure, follow up. C Planning, kick off, individual preparation, review meeting, rework, follow up. D Preparation, review meeting, rework, closure, follow up, root cause analysis. Click here for answer Correct Answer : c |
49 | Q49: Which of the following statements about static analysis is FALSE? A Static analysis can be used as a preventive measure with appropriate process in place. B Static analysis can find defects that are not easily found by dynamic testing. C Static analysis can result in cost savings by finding defects early. D Static analysis is a good way to force failures into the software. Click here for answer Correct Answer : d |